Project Impacts
Motorists are advised that there will be nightly lane closures on both i-95 southbound and northbound from 8:00 p.m. to 5:00 a.m. (sunday through thursday). Project limits are from Exit 74 to exit 75.
2024 Project Activities Include:
Utility Work:
- All utility work will be completed this winter.
I-95 74 Southbound On/Off Ramp
- Installation of fill in available areas
- Completion of Retaining Wall 105 (associated with Exit 74 I-95 southbound on-ramp)
Exit 74A I-95 Northbound On-Ramp
- Rock blasting completed
- Progressing with Retaining Wall 111
- Drainage
- Roadway widening
- Installation of temporary earth retaining systems (TERS)
Latimer Brook
- Selective demolition of certain existing components of the culvert
- Installation of Retaining Wall 115
- In-water work for environmental improvements
All above activities for Latimer Brook need to be completed in order to complete Exit 74 I-95 northbound on-ramp.
Route 161
- Drainage (south side)
- Partial gas main relocation
DOT Access Road
- Progressing with Retaining Wall 111
- Fine grading in preparation for paving
Bridge 00250 (I-95 Over Route 161)
- Build new section of bridge
- Install new abutments.
- Set structural steel
- Pour bridge decks
I-95
- Retaining Wall 107
- Retaining Wall 109
- Build new temporary section of highway from Exit 74 I-95 northbound off-ramp to the new portion of bridge (this will allow for a realignment of traffic off of existing northbound lanes which will then be reconstructed)