Future Milestones

The next major milestone goal is to move into stage 5 of the construction project.  This would come with the completion of the following elements of work:

  • Reconstruction of I-95 including traffic shift
  • Installation of the middle portion of I-95 Bridge 250.
  • Construction of temporary Exit 74 off-ramp (south).